Findings
- ok
New page layouts are on the staging site
All five templates render on the staging site and passed the team's own review.
- warn
Accessibility pass is one week late
The review moved to week 43; content entry can continue in parallel.
- crit
Payment sandbox credentials expire on 20 October
Renewal needs the account owner. Without it, donation testing stops.
- info
Two volunteers join in November
They will take over content updates after launch.
Workstreams
| Workstream | Owner | Progress | Due | Status |
|---|---|---|---|---|
| Page design | Mira | 100% | 5 Oct | Done |
| Build | Tomas | 70% | 24 Oct | On track |
| Accessibility | Ana | 20% | 31 Oct | Late |
| Content entry | Lea | 45% | 7 Nov | On track |
The release settings the team agreed on:
release:
date: 2026-11-10
freeze: 2026-11-03
rollback: previous build
Progress at a glance
Budget estimate
Change the inputs; the total updates as you type. This runs entirely in the page.
Estimated total:
Your checklist
Your ticks are personal: saved for you only, and kept when you come back.
Team note
One note for everyone who can open this report. Editors can change it; readers see it read-only.
Read-only: only the report's editors, managers and owner can change the team note.
Quick questionnaire
Tell the team how the project looks from where you sit. Only the project's managers read the answers.